On 18 January 2007, Minister of Transport Jerzy Polaczek filed a proposal of detailed schedule with preparatory steps and construction works for Toll Motorway A2: Świecko – Nowy Tomyśl to the President of Executive Board, Autostrada Wielkopolska JSC.
The draft of the schedule expects the motorway section to be ready in two phases:
Nowy Tomyśl – Trzciel: May 2009,
Trzciel – Świecko: December 2009/January 2010.